At the end of July, BF&S welcomed project partners for a “Bowl Raising” event to celebrate the placement of the elevated water storage tank bowl for Lebanon Utilities in the LEAP District. It was a great opportunity to watch this impressive feat of engineering come together and recognize the incredible teamwork that made it possible.
The scale of the structure is just as impressive, with approximately 450 tons of structural and reinforcing steel, supported by more than 2,400 tons of concrete in its foundation and pedestal, and when complete, it will hold approximately 8,300 tons of water.
Congratulations to everyone involved in reaching this milestone!
Project Team:
General Contractor: Kokosing
Water Tower Contractor: Landmark Structures
Designer / Owner’s Representative: BF&S